Driving through Greensborough means dealing with changing lanes, temporary intersections and major M80 construction. Grimshaw Street is being rebuilt, Greensborough Bypass traffic arrangements are changing, and the Diamond Creek Road roundabout carries a reported 56,800 daily vehicle movements. The wider interchange project is scheduled to continue into 2028.
Quick facts
- 56,800 daily vehicle movements: RACV’s published figure for the Greensborough Bypass and Diamond Creek Road roundabout.
- October 2026: Works continue around Greensborough Highway, Greensborough Bypass and Kempston Street.
- Mid-2027: Major Grimshaw Street interchange works are scheduled to continue until this period.
- 2028: New express lanes beneath Grimshaw Street and the completed M80 interchange are scheduled to open.
- Roundabout upgrade: Nillumbik and Banyule councils have sought funding for a $300,000 feasibility study.
Grimshaw Street and Greensborough Bypass: What drivers face in 2026
The Grimshaw Street interchange connects Grimshaw Street, Greensborough Highway and Greensborough Bypass. It is one of the main construction areas in the M80 Ring Road Completion project.
Traffic must keep moving while crews rebuild the interchange. That means temporary intersections, construction barriers and changing road layouts can affect familiar journeys.
Big Build’s construction updates show how the work is progressing.
| Date or period | Confirmed work or published schedule |
|---|---|
| September 2025 | Traffic moved onto new M80 lanes and a temporary intersection |
| 30 October 2025 | Grimshaw Street east reopened after a 30-day construction program |
| May to June 2026 | Traffic transfer onto new Greensborough Bypass outer lanes was scheduled |
| July 2026 to mid-2027 | Major Grimshaw Street interchange works scheduled |
| October to December 2026 | Continuing works around Greensborough Highway, the bypass and Kempston Street |
| 2028 | Planned opening of new express lanes beneath Grimshaw Street |
The September 2026 works update confirms Greensborough Road had reopened. However, construction continues around nearby connections.
The complete October to December closure timetable could not be verified, so drivers should not assume older lane arrangements still apply.
Greensborough Bypass and Kempston Street: Lane changes and temporary turns
One major part of the bypass works involves widening the bridge over Kempston Street.
Big Build’s May 2026 notice scheduled traffic to move onto newly constructed outer lanes from early May. This would create space for bridge widening and utility relocations. The precise date the traffic switch was completed could not be confirmed.
Temporary turning arrangements are another part of the project.
Big Build scheduled signalised U-turns around Greensborough Bypass, Greensborough Highway and Grimshaw Street from late 2026 to mid-2027. These arrangements are intended to maintain traffic movements during bridge and express-lane construction. Families heading in for weekend parking at WaterMarc should allow for these changed turns.
A separate signalised U-turn north of Elder Street was scheduled to maintain access to Elder Street and Watsonia Road until late 2026.
Practical points for local drivers:
- Grimshaw Street: Follow current turning signs rather than relying on an older route.
- Greensborough Bypass: Watch for lane changes as completed sections are brought into traffic use.
- Kempston Street bridge: Allow for construction activity around the widened crossing.
- Greensborough Highway: Pay attention to temporary traffic signals and turning arrangements.
Exact U-turn locations, current lane counts and posted speed limits were not established in the research.
Diamond Creek Road roundabout: What the RACV survey found
The Greensborough Bypass, Diamond Creek Road and Civic Drive roundabout is a separate concern from the Grimshaw Street interchange works.
In October 2025, RACV identified it as the intersection respondents considered most dangerous in north-eastern Melbourne through its My Melbourne Road survey.
Respondents raised concerns about the multi-lane layout, gradient, complex movements and unsafe driving behaviour.
The survey received 12,400 responses across Melbourne. RACV and the National Transport Research Organisation assessed 364 metropolitan intersections before selecting 84 for voting.
| RACV measure | Published result |
|---|---|
| Daily vehicle movements | 56,800 |
| Campaign responses | 12,400 |
| Intersections assessed | 364 |
| Intersections selected for voting | 84 |
| Regional survey result | Most dangerous in north-eastern Melbourne |
RACV published the traffic figure in October 2025 but did not specify the underlying count year or method.
The survey result reflects driver concerns, not an official ranking by casualty-crash numbers.
For regular users, the roundabout’s layout demands attention before entering. Drivers need to judge approaching traffic, select the correct lane and maintain their path towards the intended exit.
Three useful habits at this roundabout:
- Choose the appropriate lane before entering rather than changing position late.
- Watch vehicles entering from Diamond Creek Road, Civic Drive and Greensborough Bypass.
- If an exit is missed, continue safely instead of making a sudden lane change.
Greensborough crash data: What the official records can tell us
Victoria’s Department of Transport and Planning maintains road crash records using Victoria Police reports and hospital injury information.
The verified dataset covers 1 January 2012 to 31 January 2026 and was updated on 14 September 2026. The department generally publishes monthly updates with a seven-month reporting lag.
The collection covers casualty crashes, involving fatal or injury outcomes. It does not provide a complete record of collisions causing vehicle damage only.
No verified crash totals were obtained specifically for Grimshaw Street, Greensborough Bypass or the Diamond Creek Road roundabout.
This means RACV’s survey finding cannot be treated as proof that the roundabout has the highest recorded crash count.
What can vehicle footage show at these Greensborough roads?
Footage can help explain vehicle movements where temporary intersections differ from the arrangements drivers remember.
| Location | What footage may capture | What it cannot prove alone |
|---|---|---|
| Grimshaw Street | Signals, turning movements and temporary signs | Legal fault |
| Greensborough Bypass | Lane changes, braking and barriers | Complete collision cause |
| Diamond Creek Road roundabout | Entry, exits and lane positioning | Every driver’s intentions |
| Greensborough Highway | Turning traffic and nearby vehicles | Events outside camera view |
Forward and rear recordings offer different perspectives, but neither captures everything.
Drivers considering dash cam installation in Greensborough should think about their regular routes through changing intersections and whether the recorded view could help explain an incident during construction.
Grimshaw Street and M80 upgrades: What changes by 2028?
The finished Grimshaw Street interchange is intended to separate through traffic from local journeys.
Big Build’s design places express traffic underneath Grimshaw Street while retaining dedicated lanes for local trips. It also includes a bus-priority lane in each direction and two new underpasses for pedestrians and cyclists.
These are planned features, not confirmation that every part is operating in October 2026.
The wider project will connect the M80, Greensborough Bypass and North East Link express lanes. Existing traffic lights at the M80 intersection are also intended to be removed.
| Period | Planned milestone |
|---|---|
| Late 2026 to 2027 | Progressive transfers onto new M80 structures |
| Mid-2027 | Scheduled end period for major Grimshaw Street works |
| 2028 | Express lanes and completed M80 interchange scheduled to open |
| After opening | Landscaping, median islands and finishing works |
The Diamond Creek Road roundabout is not part of this confirmed interchange opening schedule.
In October 2025, Nillumbik Council announced plans to work with Banyule Council to seek Victorian Government funding for a $300,000 roundabout feasibility study.
Nillumbik’s mayor also cited an expected 30% increase in congestion when North East Link opens in 2028. The council did not publish the underlying traffic model.
Funding approval, a final roundabout design and a construction date remain unconfirmed.
Greensborough driving FAQs: Grimshaw Street, the bypass and roundabout
Will Grimshaw Street roadworks finish before 2028?
Major interchange works are scheduled to continue until mid-2027. However, express lanes beneath Grimshaw Street are planned to open in 2028, with finishing works following.
Is the Diamond Creek Road roundabout being replaced as part of the M80 works?
No replacement project was confirmed in the research. Nillumbik and Banyule councils have sought funding to study possible upgrades, but approved construction funding and a delivery date were not verified.
Are there confirmed Greensborough Bypass closures in late 2026?
Big Build’s September 2026 update confirms continuing works during October to December, but the full closure timetable could not be verified. Drivers should check current official traffic notices before travelling.
For Greensborough motorists, the main challenge through 2028 is knowing which changes are temporary and which belong to the finished network. Grimshaw Street and the M80 are moving towards a new interchange layout, while the Diamond Creek Road roundabout remains a separate upgrade question.